Highly Recommend To Choose PK0-004 Practice Exam As the Preparation Materials

Highly Recommend To Choose PK0-004 Practice Exam As the Preparation Materials

Most business professionals who coordinate or manage small-to-medium-size projects, inside and outside of IT can choose to be a CompTIA Project+ certified to promote themselves. When preparing for CompTIA Project+ PK0-004 exam, you will be highly recommended to choose PK0-004 practice exam as the preparation materials. The actual PK0-004 practice exam contains 507 practice exam questions. The most important is all the answers have been verified by the professional experts and successful experts. Just only choose PK0-004 practice exam and read all the Q&As in PK0-004 active pdf file, we guarantee the success.

CompTIA Project+ Certification Exam PK0-004 Free Questions Below

Page 1 of 6

1. A non-stakeholder approaches the project manager and asks if certain items can be added to a project that was started two months earlier .

Which of the following constraints does this impact MOST?

2. The PM is preparing for the planning phase kickoff meeting. It is imperative for the team to focus during the meeting on the expected outcomes.

Which of the following best describes what the PM should work on FIRST?

3. A project team added a new member who has proprietary information about a competitor's product. The team member was suddenly removed from the project .

Which of the following MOST likely occurred?

4. Which of the following primary factors are used to prioritize the development of risk response strategies? ( Choose two.)

5. A subcontractor has submitted design documentation on the deliverable due date, but it will require rework. The activity is on the critical path of the project schedule .

Which of the following should the project manager do NEXT?

6. A project has a of $850,000. The project manager has identified and documented that certain key applications were not included in the scope management plan. As reported, the

CPI is 0.8, and the PMO allows only a 5% additional increment to the planned budget .

Which of the following should the project manager do NEXT?

7. Which of the following are mutually binding project documents? (Select two.)

8. Which of the following individuals is MOST likely to be a key stakeholder for the product launch phase of a project?

9. A project manager has received numerous complaints from staff concerning poor service provided by a vendor.

Which of the following steps should the project manager take FIRST to correct the problem?

10. A project coordinator notices there is a scheduling conflict with the weekly team meeting. The project coordinator submits a request to hold the meeting at a different time will not negatively impact the scheduling.

Which of the following resources has the authority to authorize this change?


 

Leave a Reply

Your email address will not be published. Required fields are marked *